North Manchester General Hospital Enabling Works

  • Client: Manchester University NHS Foundation Trust
  • Role: Project & Cost Management
  • Value: £50m
  • Sector: Healthcare

Project Overview

The programme of works includes a phased sequence of extensive enabling works across the Trust’s estate in preparation for the planned re-development of the North Manchester General Hospital, which is part of the New Hospital Programme.

In order to ready the hospital site for the re-development work under the NMGH masterplan proposals, a large scale programme of enabling works is currently underway and includes;

Provision of a 3000sqm temporary modular building to decant Trust admin services. The demolition and clearance of  ageing estate including asbestos removal works, service diversions and a new substation. The provision of a new 980 space MSCP and cycle hub. A new temporary entrance which link the MSCP back in to the main hospital. A number of temporary surface level car parks and a permanent green parking zone for Electric Vehicle Charging.  Refurbishment of existing hospital accommodation to provide decant facilities which enabling wider site phasing plan. Re-provision of memorial garden.  

Services and value added

  • Programme management, review of planning, mitigation and re-scheduling
  • Design Management and Planning Authority liaison
  • Management of large scale and complex phasing programme
  • Cost Management integrated with wider redevelopment programme
  • Team will high level of healthcare project experience